From:                                         James Quin

Sent:                                           Tuesday, December 06, 2011 11:57 AM

To:                                               Liz Kennedy

Subject:                                     FW: Creek Trail Street Lights Repairs

Attachments:                          Creek Trail Bids Street Light Repairs 11-2-2011.pdf

 

Agenda Item Number 12 with attachment.

 

From: Michael Barnes
Sent: Monday, December 05, 2011 3:32 PM
To: James Quin
Cc: Kenneth Cross; Barbara Childress
Subject: Creek Trail Street Lights Repairs

 

On 10-28-2011 a report to the Police Department was made concerning the vandalism of all street light wiring in Creek Trail Park(CTP). Consequently, public works staff requested 3 contractors to submit proposals for the rewiring of all the street lights in CTP. Attached, are the three bids received:  1) Ed’s Electric., 2) Powersource Electric Co.(PECI), and 3) Cable Electric, Inc.

A breakdown of bids received is as follow:

 

                                                                                    Ed’s Electric                                        PECI                                         Cable Electric

 

Base Bid                                                                   $17,185.00                                     $18,746.52                                   $19,600.00

 

Alternate Bids:

Circuit to pavilion                                                  + $2,300.00                                      -$2,300.00                                       No Bid

Additional Pole                                                          IIBB  (Steel)                                       IIBB  (Aluminum)                       $5,500.00

Replace wiring to top of pole (15)                      +$4,350.00                                      +$2,073.60                                       No Bid

                                                                                     _________                                    ___________                                __________

Total                                                                            $23,835.00                                    $20,820.12                                  $26,100.00    

 

IIB = Included In Base Bid

 

The low Base Bid is PECI at $16,446.52 because Ed’s Electric did not included in his base of bid $17,185.00 the cost of the circuit to the pavilion and PECI did. Therefore, comparing the same work to each bidder PECI is the low base bid. It is not known at this time if the wiring from the base of the pole to the top is required or not. This unit cost per pole is included in case any or all wiring in the pole(s) is required, provided the project is funded. If all 15 poles need rewiring from the base to the top and the circuit to the pavilion is included the total amount would be $20,820.12. Staff’s recommendation would be to award the lowest bid in the amount of $20,820.12 to PECI in case the funds are required. Staff will submit a report to the city manager when all work is completed detailing the final amount of alternate bids used.

This item is not funded in the 2011-2012 budget. Please place this item on the council’s agenda for December 13, 2011 for their consideration. Please contact me if you have any questions.

 

 

 

 

 

Michael Barnes

Director of Public Works